Huyton Asphalt Head Office
Site
Huyton Asphalt New Offices
Client
Huyton Asphalt
Commencement Date
5th Dec 22
Description of works
Full Sparkle clean of the following areas:
Lobby/Reception
Data/Storage room
W.C. x2
Break out area
Programming room
Open plan Office areas x2
Kichen x2
Meeting room x2
Individual Offices x5
Timescale allowed
4 days
Completed on time
Yes
TSL Projects - Magna Park, Lutterworth
Site
Magna Park, Lutterworth
Client
TSL Projects
Commencement Date
11th July 2022
Full Builders Clean, External Clean and Sparkle Clean of 3x units totalling over 700,000 sq ft.
MPS5 – 186,790 sq ft, MPS6 – 211,518 sq ft, MPS8 – 330,365 sq ft
Timescale allowed
12 Weeks
Completed on time
Yes – PC achieved on all 3 units by Fri 30th Sept 2022