TSL Projects - Magna Park, Lutterworth
Site
Magna Park, Lutterworth, UK
Client
TSL Projects
Commencement Date
11th July 2022
Description of works
Full Builders Clean, External Clean and Sparkle Clean of 3x units totalling over 700,000 sq ft.
MPS5 – 186,790 sq ft, MPS6 – 211,518 sq ft, MPS8 – 330,365 sq ft
Timescale allowed
12 Weeks
Completed on time
Yes – PC achieved on all 3 units by Fri 30th Sept 2022