Fulwood clinic presents the refurbishment and structural alterations carried out at a health center. The scope of the project included updating and modifying various areas within the facility, with a particular focus on replacing floor coverings. The work was designed to enhance the functionality and aesthetic of the center while ensuring minimal disruption to its daily operations.
A challenge encountered during this project was executing construction work adjacent to normal working hours in a live environment, such as operating audiology clinics.
To address this, the team had to implement strict measures to minimize noise and ensure that disruptions were kept to an absolute minimum. This required meticulous planning and coordination to balance work commencing with the ongoing needs of the facility, ensuring a conductive environment was contained for clinic operations.